ACME Solar Share Price Rises Over 4%; Commissions Phase-I of Rajasthan BESS Project

ACME Solar Holdings Limited has commissioned Phase-I of the Battery Energy Storage Systems (BESS) component of its Rajasthan project, as per an exchange filing dated September 14, 2026.
The company completed the commissioning on September 14, 2026, through its wholly-owned subsidiary, ACME Greentech Seventh Private Limited.
53.63 MW/300 MWh Added
The commissioned phase has a capacity of 53.63 MW/300 MWh. It forms part of a 300 MW/1,581 MWh Firm and Dispatchable Renewable Energy (FDRE) project located at Village Kelan, Tehsil Chhatargarh, District Bikaner, Rajasthan.
Renewable Energy Work Continues
The battery storage facility is the only component of the project commissioned so far. The renewable energy generation component of the project remains under development, according to ACME Solar.
The company has not provided a completion timeline for the renewable energy generation component in its disclosure. The commissioned BESS capacity therefore represents part of the wider 300 MW/1,581 MWh project.
COD on September 16, 2026
The commercial operation date (COD) for the commissioned BESS component is scheduled for September 16, 2026. The date comes two days after the company completed the commissioning of Phase-I.
Project Structure
ACME Solar is undertaking the BESS project through ACME Greentech Seventh Private Limited, its wholly-owned subsidiary. The storage facility is being developed as part of the larger FDRE project in Bikaner district.
Read More: HDFC Bank Share Price Surges; Two Names Submitted to RBI for MD and CEO Role!
ACME Solar Holdings Share Price Performance
As of September 15, 2026, at 12:42 pm, ACME Solar Holdings share price was trading at ₹419.40, up 4.25% from the previous closing price.
Conclusion
ACME Solar has commissioned the first 53.63 MW/300 MWh phase of its 300 MW/1,581 MWh FDRE project in Rajasthan. The renewable energy component is still under development, while the commissioned BESS is due to begin commercial operations on September 16, 2026.
Disclaimer: This blog has been written exclusively for educational purposes. The securities mentioned are only examples and not recommendations. This does not constitute a personal recommendation/investment advice. It does not aim to influence any individual or entity to make investment decisions. Recipients should conduct their own research and assessments to form an independent opinion about investment decisions.
Investments in the securities market are subject to market risks, read all the related documents carefully before investing.
Looking to invest? Open a Demat Account with Angel One and start trading seamlessly.
Published on: Sep 15, 2026, 1:08 PM IST

Team Angel One
- Indian IT Stocks in Focus; Top Five Firms Add 16,055 Employees in H1FY27 but Demand Recovery Remains Uncertain
- BPCL Share Price in Focus as Q2FY27 Net Profit Declines 22.5%
- Paradeep Phosphates Share Price in Focus; Signs MoU for ₹4,750 Crore Investment in Odisha
- Aditya Birla Real Estate Share Price in Focus as Birla Estates Announces ₹1,650 Crore Pune Project
- Bajaj Finserv Share Price in Focus; Subsidiary Names Deepak Reddy as CEO Designate